Table of Contents |
---|
Overview
Show HA setup and their Synchronization.
Pre-requisite
2 CCE (192.168.2.x) servers to be configured at DC in active-passive mode.
...
Once a day, the DC data will be synchronized with the DR.
Test Procedure
...
(In the above diagram ignore the DCDR network on the right side)
1- Setup HA APEs and check to make sure both are getting the logs and flows on the dashboard as well as on data ingest i.e., system dashboard.
...
3- Please note that the actual IP addresses may be different during test
Case I- when cce 1 and 2 are active, ape 1 and 2 are active. (This is step 1 above)
...
Demonstrate – console (ape 1 or 2 ) https:x.y.z.a
Run for 15 min
Case II – cce 1 down , repeat the steps above
Case III- cce 1 up, ape 1 down , above steps
Case Iv- cce 1 down , ape 1 down , steps
...
APE-01 will become passive APE
Expected Output
...
1- Both APEs should have the similar data sets on the performance dashboard before the test scenarios are executed.
2- At the end of Scenario-1, verify that the active APE is accessible.
3- Verify that the performance dashboard shows data over the last few minutes.
4- At the end of Scenario-2, verify that the newly active APE is accessible
5- Verify that the performance dashboard shows data over the last few minutes.